- Acceptance of access application
The marketing department (customer service center) of a city or county-level company is responsible for accepting applications for distributed power supply access, assisting project owners to fill in the access application form, and receiving relevant supporting documents and Data and organize the completion of the project site survey.
The first type of distributed power supply refers to the distributed power supply with a voltage level of 10kV and below, and the total installed capacity of a single grid connection point does not exceed 6MW.
The second type of distributed power supply refers to the distributed power supply with 35kV voltage level access, the annual self-generated self-consumption is greater than 50%; or the 10kV voltage level access and the total installed capacity of a single grid connection point exceeds 6MW, the annual self-generated self-consumption is greater than 50%. Distributed Power.
The marketing department (customer service center) of the prefecture-level company is responsible for filing the access application materials and reporting it to the prefecture-level company development department. The development department of the prefecture and city company notified the prefecture and city economic research institute (the company in the municipality is the economic research institute, the same below) to formulate the access system plan. The working time is 2 working days.
- Determine the access system scheme
The Prefectural and Municipal Economic Research Institute is responsible for researching and formulating the access system scheme. The depth of the research content of the access system is implemented in accordance with the relevant requirements of the country and the company, refer to Q/GDW 1480-2015 “Technical Regulations for Distributed Power Access to Power Grids”. The working time limit is 30 working days for the first category of projects (including 10 working days for distributed photovoltaic power generation single-point grid-connected projects, and 20 working days for multi-point grid-connected projects), and 50 working days for second category projects.
The marketing department (customer service center) of the prefecture-level company is responsible for organizing the relevant departments to examine and approve the access system scheme of the 380V access project, and issue the evaluation opinions. The working time is 5 working days.
The development department of the prefecture and city company is responsible for organizing the relevant departments to examine and approve the 35, 10kV access project (for multi-point grid-connected projects, at least one grid-connected point is 35, 10kV access) access system plan, and issue review comments and grid access opinion letters. The working time is 5 working days.
The marketing department (customer service center) of the prefecture-level or county-level company is responsible for notifying the project owner of the confirmation sheet for the access system plan for 380V access projects, or the confirmation sheet for the access system plan for 35 and 10kV access projects, and the letter of opinion on access to the power grid , the working time is 3 working days. Responsible for accepting and arranging consultations on access system solutions.
35,For the 380V access project, the marketing department is responsible for the confirmation form of the access system plan filled in by the project owner and promptly copy it to the municipal company development department, finance department, and transportation inspection department.For the 10kV connection project, the development department of the prefecture and city company is responsible for sending the confirmation form of the connection system plan filled out by the project owner and the letter of opinion on the connection to the power grid, and promptly copy it to the finance department, the transportation inspection department, the marketing department, the control center, Information and communication company, and report to the provincial company development department for the record.
The company provides project filing services for distributed photovoltaic power generation projects of natural persons. For distributed photovoltaic power generation projects constructed by natural persons using their own residences and their residential areas, the development department of the prefecture and city company will receive the confirmation of the project access system plan according to the local According to the project filing management method of the competent energy department, the project owner shall file a project with the local competent energy department on behalf of the natural person project on a monthly basis, and send a copy of the filing document to the financial department of the prefecture-level company.